Who’s setting the pace in next-generation geothermal

Published on November 25, 2026
Next-gen geothermal · 2 of 3Drivers and playersWho is pulling the market forward, and on what terms

Part 1 showed a market moving from tests to its first commercial plants. The next question is who is paying for that move.

As with advanced nuclear, we looked at every commercial agreement in our next-generation geothermal record: who signed, what they bought, and what it commits them to. The answers are different from nuclear in almost every way.

Utilities are the main buyers

About seven in ten geothermal power agreements on record have a utility, community choice aggregator or municipal buyer. Tech companies sign fewer deals, but bigger ones.

Next-gen geothermal power agreements, by type of buyer
Utilities and public buyers72%
Tech companies22%
Energy companies6%

Share of enhanced, closed-loop and superhot-rock geothermal power agreements by the buyer’s sector. “Utilities and public buyers” includes community choice aggregators and municipal buyers. Shares are rounded. Source: Net Zero Insights, November 2026.

In advanced nuclear it’s the reverse: more than half of power agreements have a tech company as the buyer. Geothermal’s buyers are mostly the organizations that run the grid and serve households: Southern California Edison, NV Energy, Clean Power Alliance and other California community choice aggregators, on 15- to 25-year contracts.

These are purchases, not options

Every geothermal agreement in our record with a known commitment level is binding, and none is a reservation or an option. Three in four are power purchase agreements: the buyer agrees to take the output on set terms once the plant runs.

The same headline, two different commitments
Advanced nuclear · Meta and TerraPowerUp to 2.8 GW

Binding agreement, but Meta funds early development of two plants and holds rights to the rest. Most of the capacity is an option.

ReservationOption
Next-gen geothermal · Google and Fervo Energy396 MW

15-year, take-or-pay power purchase agreement, delivered in four 99 MW tranches from 2028, with a parent guarantee from Alphabet.

PPAObligation

Sources: TerraPower, January 2026; Fervo Energy SEC filing, August 2026.

That makes geothermal demand easier to read. A megawatt in a geothermal agreement is, far more often, a megawatt someone has committed to pay for.

One developer holds most of the contracts

Fervo Energy is the seller in more than half of all next-generation geothermal power agreements on record. It is also the buyer in the largest supply agreement in the market: a five-year deal with Vallourec, worth up to $800 million, for the steel tubes that line its wells.

Next-gen geothermal power agreements, by seller
Fervo Energy56%
All other developers44%

Share of enhanced, closed-loop and superhot-rock geothermal power agreements on record. Source: Net Zero Insights, November 2026.

Other developers, including Eavor, Sage Geosystems, XGS Energy, Exceed Geo Energy and Rodatherm, have projects and early buyers, but none comes close to Fervo’s contract book. For buyers, that’s a concentration risk. For everyone else in the market, it’s a gap.

Europe buys heat

Of the seven European agreements on record, five are for heat, not power: district heating networks in Germany and Denmark, and Roquette’s plant in Alsace, which buys heat from the Rittershoffen geothermal plant. Two of those five heat agreements have since lost the project behind them, including enercity’s contract with Eavor in Hanover.

Heat contracts are smaller and more local than power contracts, and the buyers are mostly municipal utilities and industrial sites. In Hanover, the buyer was still there when the project was cancelled. What was missing was someone willing to own and fund the project behind the contract.

What this means

  • Demand is firm, but narrow. Buyers are signing binding purchase agreements, mostly with one developer.
  • Utilities set the terms. Tech buyers take the headlines; utilities and community choice aggregators sign most of the contracts.
  • In Europe, heat is the market. And it depends on someone being willing to own and fund the project behind the contract.

In part 3, we look at where those drivers leave gaps, and where the openings are for investors, suppliers and corporates.

Build on it

Build your own deal monitor.

Every agreement behind this article, with its buyer, seller, structure and commitment terms, is structured, sourced data you can work with directly. Teams use it to:

  • Screen new agreements each week by buyer type, structure and how binding they are
  • See which developers have firm buyers and which only have projects
  • Track heat and power agreements separately, by country and buyer

Work with it in your own AI tools through our MCP connector (Claude, ChatGPT or Copilot), in Barry, our research assistant, or as Excel workbooks. It’s part of Signals by Net Zero Insights.

InvestorsCheck what a developer has really signed before you back it.
CorporatesSee what peers are buying, from whom and on what terms.
Book 30 minutes to set it up on your market

We’re working with a small group of design partners on our advanced nuclear and next-gen geothermal data.

The post Who’s setting the pace in next-generation geothermal appeared first on Net Zero Insights.